SMITHY STREET SCHOOL, TOWER HAMLETS CONSTRUCTION OF NEW EXTENSIONS & INTERNAL WORKS

• Client: London Borough of Tower Hamlets
• Contract: Arcos Consultancy Ltd
• Value £1.2 Milion
• April 2010 – February 2010

Brief:

The works were carried out in 5 phases, as follows:-
(i) Phase 1 Construction of altro storey extension to form a Nursery at ground floor level, Extended Schools Use Room at first floor level, together with a new main entrance to the school and lift installation.

(ii) Phase 2 Refurbishment of the existing East Wing of the school to form new Admin/Reception Area/Head Teachers Office and Nursery Toilets at ground floor level, Staff Room at first floor level, together with a new lift installation serving all floors of the building.

(iii) Phase 3 Refurbishment of part of the existing ground floor of the main building, to form new Deputy Heads Office, Kitchen, Storage and ground floor Staff WC’s.

(iv) Phase 4 Relocation of the Main Hall from first floor to ground floor level.

(v) Phase 5 Reconfiguration of the first floor Hall.