painting and repairs to space frame

Site Preparation and Access Control within the Great Hall

The project commenced with the essential step of attending the significant Great Hall and carefully implementing barrier measures to establish a secure and well-defined working zone.

Installation of Protective Covering for Glazed Areas

To ensure the preservation of delicate glazing elements, 18mm plywood sheets were precisely laid onto the glazing bars, with a designated quantity allocated for each project phase.

Multi-Method Approach to High-Level Decoration

The complex decorative work was expertly carried out by a team utilizing both traditional scaffolding structures and specialized abseiling techniques to access all required surfaces.

Thorough Preparation of Metal Components

All metalwork underwent a comprehensive surface preparation process, involving the removal of any unsound paint to ensure proper adhesion of the subsequent protective layers.

Specialized Abseil Team for Structural Reinforcement

A dedicated abseil team with welding expertise was engaged to address specific structural requirements, with the precise scope of their work informed by a detailed aerial survey.

Application of a Comprehensive Protective Coating System

Adhering strictly to the manufacturer’s guidelines, a full specification coating system was applied, including a two-part primer in Aluminium, followed by a durable topcoat in Dark Aluminium for long-term protection and the desired finish.